K-8 School

Project Update March 21, 2023: Work to reconfigure parking lots is beginning. Floor removal and other renovations and modifications continue inside the building. Lots of fresh paint on the walls!

Project Update January 30, 2023: K-8 school progress update: Phase 1: Ceiling grid and lighting installation in hallways has started. Phase 2: Demolition continues including the removal of flooring. The contractor is also prepping walls for painting.

Project Update December 19, 2022: K-8 school progress update: Phase 1, replacement of all HVAC systems, is nearing completion. Phase 2, renovations and modifications, has started.